Construction Update October 2026

Construction is moving forward on site. The structure has reached the 12th floor. Windows are being installed on level 6 and 7. Steel studs for interior walls have reached levels 1 and 2. Rough-ins for plumbing, electrical, and mechanical are also on levels 1 and 2. The parking garage is nearly now nearly complete. Roofing